Question: 3.1 Consider the below parts flow pattern information. The sequential arrangement of the departments from start to finish are: A-B-C-D-E-F-G. 2 FPM2601/101/3/2022 3.1.1 Construct a

3.1 Consider the below parts flow pattern information. The sequential arrangement of the departments from start to finish are: A-B-C-D-E-F-G. 2 FPM2601/101/3/2022 3.1.1 Construct a From-to-Chart for the above table. (16) 3.1.2 Calculate the efficiency of the From-to-Chart. (4)