Question: 31.Assuming the tolerable deviation rate is 5%, the expected population deviation rate is 3%, and the allowance for sampling risk is 2%. What should an
31.Assuming the tolerable deviation rate is 5%, the expected population deviation rate is 3%, and the allowance for sampling risk is 2%. What should an auditor conclude if test of 100 randomly chosen documents reveal 4 deviation?
a.Accept the sample results as support for assessing control risk below the maximum level because the tolerable deviation rate less the allowance for sampling risk equals the expected population deviation rate
b.Assess control risk at the maximum level because the sample deviation rate plus the allowance for sampling risk exceeds the tolerable deviation rate
c.Assess control risk at the maximum level because the tolerable deviation rate plus the allowance for sampling risk exceeds the expected population deviation rate
d.Accept the sample result as support for assessing control risk below the maximum because the sample deviation rate plus the allowance for sampling risks exceeds the tolerable rate
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts