Question: 36. The project management triangle is a simple communication model. What goes in the middle of the triangle? a. Cost b. Schedule c. Quality d.
36. The project management triangle is a simple communication model. What goes in the middle of the triangle?
a. Cost
b. Schedule
c. Quality
d. Objectives
37. Projects may have problems because of team members that are selected to work on the project. In other words, people are needed to make projects work, and sometimes certain people are better suited for individual work than project work.
Group of answer choices
True
False
38. The Work Breakdown Structure (WBS) is a random listing of what must be done during a project.
True
False
39.The lowest level of the Work Breakdown Structure is time, in weekly buckets.
True
False
40. A __________ Diagram is a model used to visually show project activities and their sequential relationships by use of nodes and arrows.
a. Project
b. Triangle
c. Network
d. System