Question: 37)What is the expected project completion time? A.1579 seconds B.1481seconds C.1234 seconds D.2124seconds 38)Which activities are on the critical path? A.2, 3, 4, 5, 13
37)What is the expected project completion time?
A.1579 seconds
B.1481seconds
C.1234 seconds
D.2124seconds
38)Which activities are on the critical path?
A.2, 3, 4, 5, 13
B.1, 6, 7 ,8, 9, 10, 11, 12, 14, 15
C.2, 3, 4, 8, 12, 15
D.1, 2, 3, 6, 11, 13, 15
39)What is the latest start time for "place breadsticks in oven and cook"?
A.690 seconds
B.360 seconds
C.1467 seconds
D.1037 seconds

Use the following data for problems 37 39: Crusty's pizza management has been recording data regarding the time it takes to make a pepperoni pizza and bread sticks (see table): Activity Predecessors Time (seconds) 1. Weigh dough 45 2. Make carry out box 15 3. Weight Cheese 35 4. Measure 150z of secret sauce 48 5. Roll out bread sticks l 215 6. Spin dough to proper size 1 180 7. Shape dough on pizza pan 6 64 8. Spread the secret sauce 4, 7 23 9. Place 35 pepperonis 8 65 10, Sprinkle cheese on pizza 3, 9 43 11. Add 15 pepperonis 10 24 12. Place pizza in oven & cook 11 900 13. Place breadsticks in oven & cook 5 330 14. Slice pizza 12 23 15, Place in carry out box 13,14 114 37) What is the expected project completion time? A. 1579 seconds 3. 1481 seconds c. 1234 seconds D, 2124 seconds 38) Which activities are on the critical path? AZ, 3, 4, 5, 13 B. l, 6, 7 ,8, 9,10,11,12,14,15 c2, 3, 4, 8, 12, 15 13.1, 2, 3,6,11,13,15 39) What is the latest start time for \"place breadsticks in oven and cook\"? A. 690 seconds B. 360 seconds c. 1467 seconds I). 1037 seconds Use the followin_ data for roblems 40 (all times are da 5): Activity 40) Which of the following is true? A. The normal time to complete the project is 90 days and the shortest time is 63 days B. The normal time is complete the project is 151 days and the shortest time is 101 days c. The normal time to complete the project is 85 days and the shortest time is 51 days a. The normal time to complete the project is 121 days and the shortest is 85 days
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts