Question: ( 4 0 points total ) A very long ( into the page ) embankment is constructed over a layered system of sand and clay,

(40 points total) A very long (into the page) embankment is constructed over a layered system of sand and clay, as shown in the schematic below. The properties shown for the clay were obtained by conducting a laboratory consolidation test on a specimen prepared from an undisturbed sample collected at the mid-depth of the clay layer.
(a)(10 pts) The embankment soil was excavated from a local borrow area. The in-situ phase properties of the soil in the borrow area were w=10.0% and S=45%. Given Gs=2.70, how many cubic yards of borrow soil, (total volume) had to be excavated to construct a 100-ft-long (into the page) portion of the embankment?
(b)(15 pts) Determine the effective stress (psf) at the center of the clay layer, directly under the center of the embankment, assuming that the the embankment has been in place for a very long time.
(c)(15 pts) How much ultimate settlement (inches) you would expect at the center of the embankment crest due to primary consolidation of the clay caused by the embankment load?
( 4 0 points total ) A very long ( into the page

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!