Question: ( 4 0 pts . ) Given the following intersection geometry, volumes, and information, ( 1 ) Determine the minimum number of phases needed for
pts Given the following intersection geometry, volumes, and information,
Determine the minimum number of phases needed for the pretimed signal control.
Draw the phase diagram showing the movements for each phase indicate clearly protected vs permitted movements
Determine the critical lane group for each phase.
Determine the optimal cycle length to minimize delay ie Webster's method
Compute the yellow and allred intervals for each phase.
Compute the effective and actual green times for each phase.
Determine whether the actual green times are greater than their respective minimum pedestrian green times. Pedestrians should be served during the phases that serve the vehicular through movements.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock