Question: ( 4 0 pts ) Making one item necessitates the completion of the following nine tasks, each of which has precedence relationships. Assuming that each

(40 pts) Making one item necessitates the completion of the following nine tasks, each of
which has precedence relationships.
Assuming that each task is executed at a distinct workstation, similar to the illustrated assembly line
below:
a.(3 pts) Is this assembly line able to fulfill all the precedence requirements? Why?
b.(3 pts) What is the cycle time of the corresponding production line? Why?
c.(3 pts) What is the production rate of the corresponding production line?
d.(3 pts) Calculate the efficiency of this production line.
e.(3 pts) Is it possible to enhance the efficiency of the line while maintaining the same cycle
time of 3.4 minutes in the given scenario? If so, how can it be accomplished?
f.(5 pts) Assume that in the aforementioned example, the desired production rate is 12 units per
hour. Can this be achieved or is this feasible? Please answer with "Yes" or "No" and provide
the reasoning behind your answer.
g.(5 pts) What is the minimum possible number of stations (NMin) that can accommodate this
production (12 units per hour) rate?
h.(15 pts) Compare the efficiency of the above example by solving it based on the largest
processing time and the number of successor rules (Please consider required production rate =
12 units/hour.)
 (40 pts) Making one item necessitates the completion of the following

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!