Question: 4 1 5 points A ) . Describe the framework of the risk management plan. How can it effectively address the construction uncertainty? ( 5

4
15 points
A). Describe the framework of the risk management plan. How can it effectively address the construction uncertainty? (5 points)
B). For the following project baseline plan and progress report, compute the BAC, EV, SPI, and CPI for the end of period 5. What is the forecasted project cost upon completion (EAC) based on maintaining the current CPI? What will you write in your progress report based on the EV assessment? (10 Points)
\table[[Task,PV,1,2,3,4,5,6,7,8,9,10,11],[1,8,4,4,,,,,,,,,],[2,40,,,10,10,10,10,,,,,],[3,30,,,10,15,5,,,,,,],[4,20,,,10,10,,,,,,,],[5,40,,,,,,20,20,,,,],[6,60,,,,,20,20,10,10,,,],[7,20,,,,,,,,10,10,,],[8,30,,,,,,,,,,20,10],[Period PV Total,4,4,30,35,35,50,30,20,10,20,10],[Cumulative PV Total,4,8,38,73,108,158,188,208,218,238,248]]
Status Report
\table[[Task,% Complete,PV,EV,AC],[1,100%,,,10],[2,60%,,,30],[3,100%,,,40],[4,50%,,,20],[5,0%,,,0],[6,30%,,,24],[7,0%,,,0],[8,0%,,,0]]
 4 15 points A). Describe the framework of the risk management

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!