Question: 4 . 1 6 A field compaction control test was conducted on a compacted lift. The mass of the material removed from the hole was

4.16 A field compaction control test was conducted on a compacted lift. The mass of the
material removed from the hole was 1820 g and the volume of the hole was found to be
955cm3. A small sample of the soil lost 17 g in the drying test and the mass remaining after
drying was 94 g . The laboratory control test results are shown in Fig. P4.16.
a. If end-product specification requires 100% relative compaction and
optimum -3% to (optimum +1%), determine the acceptability of the field
compaction and state why this is so.
b. If it is not acceptable, what should be done to improve the compaction so that it will
meet the specification?
Figure P4.16
4 . 1 6 A field compaction control test was

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!