QUESTION 1
A network consists of the following list. Times are given in weeks.
\table[[Activity,Preceding,Optimistic,Probable,Pessimistic],[A,--,5,11,14],[B,--,3,3,9],[C,--,6,10,14],[D,A, B,3,5,7],[E,B,4,6,11],[F,C,6,8,13],[G,D, E,2,4,6],[H,F,3,3,9]]
(a) Draw the network diagram.
(b) Calculate the expected duration and variance of each activity.
(c) Calculate the expected duration and variance of the critical path.
(d) Calculate the probability that the project will be completed in less than 28 weeks.
CHAPTER ON FORECASTING
QUESTION 2
The demand for electrical power at Subang Jaya, Selangor, Malaysia over the period of 2017 to 2023 is shown in the following tables, in megawatts.
Tenaga Nasional Berhad (TNB) wants to forecast 2024 demand by fitting the straight-line trend to those data. Besides the trend analysis, the northern regional TNB general manager wants also the strength of the association between the year and the power demand in Subang Jaya
\table[[Year,\table[[Electrical],[Power],[Demand]]],[2017,74],[2018,79],[2019,80],[2020,90],[2021,105],[2022,142],[2023,122]]
 4:17 Assignment 2- to be submitted.pdf CHAPTER 3- PROJECT MANAGEMENT QUESTION

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!