Question: 4 1 . If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and
If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds goodEFESDLSLFDLF LS DD EFESall of the above If TL is the largest allowable event occurrence time, total activity slack s is equal tolatest start time earliest start timelatest finish time earliest finish time EFTTLEFTall of the abovenone of the above In a PERT chartall activities should be numberedonly important activities should be numberedonly critical activities are numberedonly selected activities are numberedno activity is numbered.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
