Question: 4 . 1 The estimate for a five - story office building included 7 2 doors on each of the upper three floors. In developing
The estimate for a fivestory office building included doors on each of the upper three floors. In developing the bid, the estimator used a production rate of carpenter manhours to hang a door. The project superintendent is organizing the carpenter crews to include three carpenters per crew. What is the duration in days of the activity to hang all the doors on the upper three floors? Assume an hr workday.