Question: 4 2 0.75 4 What's the difference between Control Quality and validate Scope Control Quality is performed by the project manager, while Validate Scope is

4 2 0.75 4 What's the difference between Control
4 2 0.75 4 What's the difference between Control Quality and validate Scope Control Quality is performed by the project manager, while Validate Scope is done by the sponsor Control Quality is done at the end of the project, while Validate Scope is done throughout the project Control Quality in performed by the sport, while Validate Scope is done by the project manager Control Quality and looking for defects in deliverables, while Validate Scope means validating that the product is acceptable to the stakeholders