Question: 4 2 points The project manager is working with cost estimates in order to establish a cost baseline for measuring project performance. What process is

4
2 points
The project manager is working with cost estimates in order to establish a cost baseline for measuring project performance. What process is this?
Estimate Costs
Determine Budget
Cost Management
Control Costs