Question: 4) [2 points] (This Question is related to Chapter 3 section Determining the Project Schedule) A network consists of the activities in the following list.

4) [2 points] (This Question is related to
4) [2 points] (This Question is related to Chapter 3 section Determining the Project Schedule) A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A 8 B - 3 C A 7 D A, B E C F D 9 I (a) Draw the network diagram. (b) Calculate the ES, EF, LS, LF, and Slack for each activity. (c) What is project completion time? 3 4