Question: 4 . 3 Construct a bar chart to use in managing the construction of a single - spanbridge. The identified activities are Drive piling west

4.3 Construct a bar chart to use in managing the construction of a single-spanbridge. The identified activities are Drive piling west abutment (WA),2 days Drive piling east abutment (EA),2 days Construct WA cast in place pile cap, 3 days Construct EA cast in place pile cap, 3 daysEach pile cap requires 5 days curing time before the precast girders can beplaced. Set girders, 1 day Construction of cast-in-place concrete deck, 7 days Cure deck, 14 days West and east concrete approach slabs, 5 days eachThere is only one crane available for pile driving and setting girders. Thecompany plans to use only one crew of carpenters and finishers for theconcrete work.a. What is the project duration?b. Are the two construct approach slab activities critical to the projectcompletion?4.4 Construct a bar chart to use in managing the construction of a single-spanbridge as described in Question 4.3. Again, there is only one craneavailable for pile driving and setting girders, but the company now plans touse two carpenter crews for the concrete work. The deck construction willtake only 5 days using two crews. a. What is the project duration? b. If two cranes were available for pile driving, what would be theproject duration?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!