Question: 4 . 3 Construct a bar chart to use in managing the construction of a single - span bridge. The identified activities are Drive piling

4.3 Construct a bar chart to use in managing the construction of a single-span bridge. The identified activities are
Drive piling west abutment (WA),2 days
Drive piling east abutment (EA),2 days
Construct WA cast in place pile cap, 3 days
Construct EA cast in place pile cap, 3 days
Each pile cap requires 5 days curing time before the precast girders can be placed.
Set girders, 1 day
Construction of cast-in-place concrete deck, 7 days
Cure deck, 14 days
West and east concrete approach slabs, 5 days each
There is only one crane available for pile driving and setting girders. The company plans to use only one crew of carpenters and finishers for the concrete work.
a. What is the project duration?
b. Are the two "construct approach slab" activities critical to the project completion?
4 . 3 Construct a bar chart to use in managing

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!