Question: 4 . 3 Construct a bar chart to use in managing the construction of a single - span bridge. The identified activities are Drive piling
Construct a bar chart to use in managing the construction of a singlespan bridge. The identified activities are
Drive piling west abutment WA days
Drive piling east abutment EA days
Construct WA cast in place pile cap, days
Construct EA cast in place pile cap, days
Each pile cap requires days curing time before the precast girders can be placed.
Set girders, day
Construction of castinplace concrete deck, days
Cure deck, days
West and east concrete approach slabs, days each
There is only one crane available for pile driving and setting girders. The company plans to use only one crew of carpenters and finishers for the concrete work.
a What is the project duration?
b Are the two "construct approach slab" activities critical to the project completion?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock