Question: 4. (3 Points) Using the BOM shown below. 120 x2*4= A 1 week 1+2+3=6 B(2) 2 weeks C14 1 week E (2) 1 week D(4)

4. (3 Points) Using the BOM shown below. 120
4. (3 Points) Using the BOM shown below. 120 x2*4= A 1 week 1+2+3=6 B(2) 2 weeks C14 1 week E (2) 1 week D(4) 3 weeks G(1) 1 week H (4) 1 week D (6) 3 weeks F(2) 2 weeks 120 x2 240 x 2 = 480x 2 = 960 a. Assuming you have no material on hand, how many of part D will be needed if 120 units of end item A are needed? 960 + 2,880 = 3,840 b. How many F's? 960 c. What is the cumulative lead time? 6 weeks Assuming you have the following on hand quantities Part F G On hand 100 100 d. What is the net requirements for F? e. What is the gross requirements for H