Question: 4 . 4 Construct a bar chart to use in managing the construction of a single - span bridge as described in Question 4 .
Construct a bar chart to use in managing the construction of a singlespan bridge as described in Question Again, there is only one crane available for pile driving and setting girders, but the company now plans to use two carpenter crews for the concrete work. The deck construction will take only days using two crews.
a What is the project duration?
b If two cranes were available for pile driving, what would be the project duration?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
