Question: 4 5 6 7 8 9 10 N Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball

4 5 6 7 8 9 10 N Shown below is a partially

4 5 6 7 8 9 10 N Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: Ball bearings Order Policy: 500 units Lead Time: 1 week Quantity Week on Hand: 400 1 Forecast 350 400 250 Customer orders 300 350 250 300 150 150 150 50 50 (booked) Projected on-hand inventory MPS quantity 500 550 450 300 350 350 450 350 50