Question: 4 5 . In a phased project, phase end meetings are used to sign - off on the deliverables associated with that phase. These phase
In a phased project, phase end meetings are used to signoff on the deliverables
associated with that phase. These phase end points typically provide a good
opportunity to evaluate the progress and performance in that particular phase. Which
of the following terms is synonymous for phase end?
a Phase exits
b Kill points
c Milestones
d All of the above
Which of the following are inputs to the Develop Project Management Plan
process?
a Project charter
b Enterprise environmental factors
c Expert Judgment
d Both a and b
Which of the following processes describes the collection, measurement and
distribution of performance information, and measuring the health of the project to
identify project areas that require corrective or preventive actions?
a Direct and manage project execution
b Monitor and control project work
c Integrated change control
d None of the above
In a crime prevention software development project for a municipal organization, a
steering committee is responsible for approving all deliverables before they are
transferred to operations. This steering committee is made up of directors from three
different municipal agencies. If the steering committee approves the transfer of
deliverables with a vote, which of the following statements is correct?
a The project is in the close scope phase.
b The project is in the close project phase.
c The project is in the close procurements phase.
d The project is in the validate scope phase
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock