Question: #4 a 4. a) A project to build a 4 sided square fence has the following status at the end of the third day. The

#4
a 4. a) A project to build a 4 sided square fence has the following status at the end of the third day. The Budgeted cost is $1000/day and Each side is expected to take 1 day. Calculate i) The EAC for the project( 2+3 marks) 6 ii) The Estimated time to complete the project(2 +2 marks) DAY1 DAY 2 DAY 3 DAY 4 Completion 100% 100% 60% 0% Actual Cost $1000 $1200 $600 0Step by Step Solution