Question: 4- a) b) Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project. Normal

4- a) b) Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project. Normal Minimum Crash Cost Time Time ($/day) 16 $50 $30 Activity A B E IF $380 $420 $440 10 16 A 16 18 $400 Leave blank 3 2 15 $40 $80 $100 Predecessor B C A D, E
 4- a) b) Use the information in the table (all times

Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project. a) $380 b) $420 c) $440 d) 5400 Leave blank