Question: 4 A carpenter, engineer, and plumber are available to perform certain tasks. Each person can perform only one task in the allotted time. There are

44 A carpenter, engineer, and plumber are

A carpenter, engineer, and plumber are available to perform certain tasks. Each person can perform only one task in the allotted time. There are four tasks available, three of which must be done. The cost matrix is shown below. Draft Frame Solder Wire Carpenter $6 $2 $4 $10 Engineer $7 $5 $11 $3 $1 Plumber $8 $5 $12 Use Hungarian algorithm to determine which person should be assigned to which job to minimize total cost? Write the optimal assignments and calculate the total cost