Question: 4. A small software development project atKrishna Dhir's firm has five major activities. The times are estimated and provided in thetable below: Activity Immediate Predecessors
4. A small software development project atKrishna Dhir's firm has five major activities. The times are estimated and provided in thetable below:
Activity Immediate Predecessors A M B
A - 2 5 8
B - 3 6 9
C A 4 7 10
D A 2 5 14
E B 3 3 3
a) The expected completion time for this project is ____________
b) The project variance value of completion time is ____________