Question: 4 . Consider the following tasks, along with their duration and required predecessors. ( 3 0 points ) ID Description Precede ID Duration A Complete

4. Consider the following tasks, along with their duration and required predecessors. (30 points)
ID Description Precede ID Duration
A Complete Foundation -6
B Connect Plumbing A 6
C Install Drywall A 2
D Paint Interior Walls C 4
E Install Trim Carpentry D 3
F Install Windows A 4
G Paint Exterior Walls F 1
H Complete Inspection B, E, G 0
I Attain Client Approval H 2
J Close Sale I 1
a. Draw the PERT flow, labeling ECT and LCT for each event. Please embed the drawing in this document, either in electronic format such as MS Visio or hand-drawn sketch.
b. Determine the critical path time and available slack time.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!