Question: 4.) During 2022 Fat Cat Construction started a construction job with a contract price of $2,500,000. The job was completed in 2024. The following information
4.) During 2022 Fat Cat Construction started a construction job with a contract price of $2,500,000. The job was completed in 2024. The following information is available.
|
| 2022 | 2023 | 2024 |
| Costs incurred to date | $600,000 | $1,435,000 | $2,100,000 |
| Estimated costs to complete | 1,400,000 | 615,000 | -0- |
| Billings to date | 100,000 | 500,000 | 2,500,000 |
| Collections to date | 100,000 | 300,000 | 2,000,000 |
Instructions:
Compute the amount of gross profit to be recognized each year assuming the percentage-of completion method is used.
Prepare all necessary journal entries for 2023.
(c) Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
