Question: 4. Eighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case) of J have been

4. Eighty units of end item E are needed at the

4. Eighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case) of J have been ordered and one case is scheduled to arrive in week 3, one in week 4, and one in week 5. Note: I must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 units of B and 20 units of J now on hand. Lead times are two weeks each for E and B, and one week for J. E B(2) J(3) J(4) F(2) a. Prepare a material requirements plan for component J