Question: 4. Exercise Earned Value Calculation. Based on Table 7-3 and 7-4, calculate the values and fill out Table 1 (review section 7-6). (20 points) Table.

 4. Exercise Earned Value Calculation. Based on Table 7-3 and 7-4,
calculate the values and fill out Table 1 (review section 7-6). (20

4. Exercise Earned Value Calculation. Based on Table 7-3 and 7-4, calculate the values and fill out Table 1 (review section 7-6). (20 points) Table. 7-4. Earned Value Formulas Term Earned value (EV) Cost variance (CV) Schedule variance (SV) Cost performance index (CPI) Schedule performance index (SPT) Estimate at completion (EAC) Estimated time to complete Formula EV -- PV to date. RP CV - EV- AC SV EVP CPI EVAC SPL EN/P EAC - BAC/CPI Original time estimate/SP! Week 1 TABLE 7-3 Earned value calculations for Activity Earned value (EV) Planned value (PV) Actual cost (AC) 5.000 10,000 15,000 * Additional information Budget at completion (BAC): 100,000 Original time estimate: 12 months Table 1. Answers for the Earned Values Activity Value Schedule variance (SV) Cost performance index (CPD) Schedule performance index (SPI) Estimate at completion (EAC) TABLE 7-3 Earned value calculations for one activity after Week 1 Activity Earned value (EV) Planned value (PV) Actual cost (AC) Week 1 5,000 10,000 15,000 *Additional information Budget at completion (BAC): 100,000 Original time estimate: 12 months Value Table 1. Answers for the Earned Values Activity Schedule variance (SV) Cost performance index (CPI) Schedule performance index (SPI) Estimate at completion (EAC) Estimate time to complete

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!