Question: 4. Given the network and cost information below, develop a Financial Requirements Schedule and Budget Make a table of your budget, assuming costs are distributed

4. Given the network and cost information below, develop a Financial Requirements Schedule and Budget Make a table of your budget, assuming costs are distributed linearly. Activity Duration ES LS EF LF Slack Budget 1-2 5 0 12 7 25 1-3 0 B 48 14 5 6 11 5 30 2-5 5 12 B 15 7 9 34 3 a 8 11 11 12 4-5 4 11 11 15 15 20 Assume the following information has been collected for you. Complete the Current Project Status Report given on the next page (i.e. page 3 ). From your completed report, develop a revised budget requirements table. What information would you offer at the next Project Management meeting ? (6)