Question: 4 . Individual Problems 4 - 4 Your company is contemplating bidding on an RFP ( Request For Proposal ) to produce 1 0 0

4. Individual Problems 4-4
Your company is contemplating bidding on an RFP (Request For Proposal) to produce 100,000 units of a specialized part. Suppose, however, that the requesting company really needs only 90,000 units of the part. Also assume that, because the part is specialized, potential suppliers do not yet possess the machines and factories needed to produce it and that overhead expenses involved in production have yet to be incurred.
Suppose the average costs of all potential suppliers are as follows:
Units
Average Total Cost
(Dollars Per Unit)
90,00011100,00010
True or False: The requesting company can solicit lower bids by requesting 100,000 units as opposed to 90,000.
True
False

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Economics Questions!