Question: 4. Information about a project is given below. Answer the following questions based on the information Activity Normal Time (Week) Immediate predecessor Additional crashing cost

4. Information about a project is given below.

4. Information about a project is given below. Answer the following questions based on the information Activity Normal Time (Week) Immediate predecessor Additional crashing cost Crash time (after crashing) (Hafta) 3 Normal Time Cost (S) 6000 3000 4000 10 5500 B 6 2 C 4 6 is A, B A, B, E 2000 500 4000 600 D 4 5000 6000 E 4 3 8000 2000 F G C D F, H C D 2 10 10 4000 15000 H 5 3 1000 Perform Critical Path Method on the below network diagram. (10 points) (If you do not answer this part, parts (b), (c), (d), (e), and (1) will not be graded.) A C F G B D H E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!