Question: 4 Motors are assembled in a process with two resources. The first resource has a capacity of 14 motors per hour. The capacity of the

4 Motors are assembled in a process with two
4 Motors are assembled in a process with two resources. The first resource has a capacity of 14 motors per hour. The capacity of the second resource is 12 motors per hour. The first resource has 3 workers and the second resource has worker Demand for this process is 0.84 motors per hour Wages are $23 per hour Instruction Round your answer to four decimal places What is the cost of direct labor (in sy per un 3 00 18:14