Question: 4 points Budgeted costs for Work Package Develop script - Write 1st draft $700 - Research history $1500 - Pay copy editors $250 Budgeted costs

4 points Budgeted costs for Work Package "Develop
4 points Budgeted costs for Work Package "Develop script" - Write 1st draft $700 - Research history $1500 - Pay copy editors $250 Budgeted costs for Work Package "Prepare location" Find location $200 Rent location $5000 Create set $10,000 Based on the information above, assume that this project is complete and that all tasks in the two work packages complete the project when they finished Now, calculate the cumulative earned value (CEV) for this project. O $15,200