Question: 4 points The following table identifies the activities required to complete a project, and their dependencies; Immediate predecessor(s). Activity A B D E F The

4 points The following table identifies the

4 points The following table identifies the activities required to complete a project, and their dependencies; Immediate predecessor(s). Activity A B D E F The critical path/s is/are; Duration 6 5 4. 3 5 A A B,C C,D DE ABDEF ACEF ACDEF ABDF