Question 4 of 50 -75 Current Attempt in Progress The master budget of Coronado Industries shows that the planned activity level for next year is expected to be 50000 machine hours. At this level of activity, the following manufacturing overhead costs are expected: Indirect labor Machine supplies Indirect materials Depreciation on factory bullding Total manufacturing overhead $750000 200000 150000 110000 $1210000 A flexible budget for a level of activity of 60000 machine hours would show total manufacturing overhead costs of O $1342000 O $1210000 $1430000 O $1452000