Question: 4. T01.E05 during pilot line operations, your contractor has identified design characteristics that are resulting in integration issues with lower than expected production rates. The

4. T01.E05 during pilot line operations, your contractor has identified design characteristics that are resulting in integration issues with lower than expected production rates. The affected components will require redesign of the interfaces and updated work procedures for the shop floor. The technical changes may impact the programs readiness for the next phase of production. What manufacturing readiness level should you assess for this scenario? a. MRL 6 b. MRL 5 c. MRL 8 d. MRL 10