Question: 4 The partially completed inventory record for the rotor subassembly in the table below shows gross requirements, scheduled receipti, lead me and current on hand

4 The partially completed inventory record for
4 The partially completed inventory record for the rotor subassembly in the table below shows gross requirements, scheduled receipti, lead me and current on hand very - Complete the last thrown of the record for an FO of 140 units. (Enter your response as integers A response of Valent to being noteicable) Item for assembly LO SFOQ-140 Land Time: 2 weeks Week + 2 3 5 6 2 Gross 55 45 75 75 75 requirements 75 Scheduled 140 och Projected on hand 20 Inventory Planned receipts O 10 00 DO