Question: 4. The table and graph below represent a contractors overdraft requirements for a project. Complete the table for costs, markup. total worth. retainage. and pay
4. The table and graph below represent a contractors overdraft requirements for a project. Complete the table for costs, markup. total worth. retainage. and pay received: and redraw the overdraft profile including interest. Retainage is 10%.. markup is 10%. and interest is 1% per month. The client is billed at the end of the month. Payment is received the end of the next month, to be deposited in the bank the first of the following month