Question: 4 . The table below shows a cost - plus incentive contract for a project with a floor of R 4 0 million, a target
The table below shows a costplus incentive contract for a project with a floor of R million, a target of R million and a ceiling of R million. If the client meets the floor of R million, they are entitled to an incentive of R million. If the costs reach the ceiling of R million, the client will receive no incentive. Using this information, calculate the values of A to G shown in the table below. show all calculations. No calculation, no marks.
Cost R million Customer pays R million Contractor receives R million
Target contract million AB
Actual million CD
Actual E million F
Actual million GH