Question: 4- This is from the NPV video. Given the numbers -100,000 + 18181.81 + 24,793.39 + 45,078.89 = -11,946; what is the initial investment? 100,000
4-
This is from the NPV video. Given the numbers -100,000 + 18181.81 + 24,793.39 + 45,078.89 = -11,946; what is the initial investment?
| 100,000 | ||
| 18,181 | ||
| 0 | ||
| -11,946 |
8-
One principle of the Agile Manifesto states that simplicity--the art of maximizing the amount of work not done--is essential.
True
False
10-
This is an NPV related question: A dollar today is worth the same amount as a dollar given to you 5 years from now.
True
False
11-
This question is related to risk. Transferred means to buy insurance or write contracts that get someone else to absorb the negative impacts of a risk should it manifest itself
True
False
12-
This question is based on the present value video. In the formula PV=(fv/((1+i)^n)), what does "n" represent?
| transition period. | ||
| Typical investment amount | ||
| Temporary risk event count. | ||
| time;typically in years |
13-
According to PMI's code of Ethics: We make decisions and take actions based on the best interests of society, public safety, and the environment.
True
False
14-
A successor activity cannot start until a predecessor activity has finished. That is, you need to finish activity A before you can start activity B.
| A. | Finish to start | |
| B. | Finish to finish | |
| C. | End to End | |
| D. | start to finish |
15-
This is an NPV related question. Given the numbers -100,000 + 18181.81 + 24,793.39 + 45,078.89 = -11,946; we should do the project.
True
False
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts