Question: 4. Use the information in partially completed Table 1. What is the projected on-hand inventory in week 5? A) 0 units B) 35 units C)

4. Use the information in partially completed Table 1. What is the projected on-hand inventory in week 5? A) 0 units B) 35 units C) 40 units D) 75 units 5. Use the information in partially completed Table 1. What is the MPS start quantity in week 2? A) 0 units B) 20 units C) 40 units D) 80 units 6. Use the information in partially completed Table 1. What is the available-to-promise (ATP) inventory in week 5? A) 0 units B) 35 units C) 53 units D) 80 units
Table 1 Item B Order Policy: 80 units Lead Time: 1 week Week 4 7 35 5 Quantity on Hand 601 Forecast Customer orders (booked) 60 20 Projected on Hand MPS quantit MPS start Available-to-promise 2 40 3 40 15 5 40 6 40 8 35 50 40 45 12 4. Use the information in partially completed Table 1. What is the projected on-hand inventory in week 5? A) 0 units B) 35 units C) 40 units D) 75 units 5. Use the information in partially completed Table 1. What is the MPS start quantity in week 2? A) 0 units B) 20 units C) 40 units D) 80 units 6. Use the information in partially completed Table 1. What is the available-to-promise (ATP) inventory in week 5? A) 0 units B) 35 units C) 53 units D) 80 units
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts