Question: 4. Which methodologies can be used to break project objectives into achievable project deliverables? a) Define the main project objective and break it down into
4. Which methodologies can be used to break project objectives into achievable project deliverables? a) Define the main project objective and break it down into major deliverables, then further break those deliverables into smaller tasks or work packages to provide a Work breakdown structure (WBS). b) Create a risk assessment to identify, analyse, and evaluate potential risks that could impact the success of a project. c) Create time and cost estimates to determine how much time and money will be required to complete the project d) Define objectives using the SMART criteria (Specific, Measurable, Achievable, Relevant, Time-Bound)