Question: 4. You are SW engineer at Petro SW Developers. A year ago , your manager announced that your next product would compromise 8 files, 48
4. You are SW engineer at Petro SW Developers. A year ago , your manager announced that your next product would compromise 8 files, 48 flows, 91 processes.
a. using FFP metric, determine its size.
b. for Petro SW Developers, the constant d in equation has been determined to be $1021. What cost estimate did the FTP metric predict?
c. the product recently was completed at a cost of $135,200. What does this tell you about the productivity of your development team?