Question: 41. True or false: Using the default Automatic setting allows you to control when and how Microsoft Project applies the leveling calculations. 42. True or
41. True or false: Using the default Automatic setting allows you to control when and how Microsoft Project applies the leveling calculations.
42. True or false: When a resource is overallocated, Resource views display the resource name in bold, red text with a Leveling indicator.
43. . When building your project plan and assigning resources to that plan, one way to avoid resource overallocation is to ensure that resources are available as they are assigned to a task. This technique is referred to as task _________. review , leveling , assumptions , quantification
44. True or False: Microsoft Projects real value is it eliminates the requirement of human judgment, communication, and negotiation to resolve the overallocation.