Question: 4.4. Complete the following table. Lead time for the part is 2 weeks, and the order quan- tity is 50. What action should be taken?

4.4. Complete the following table. Lead time for

4.4. Complete the following table. Lead time for the part is 2 weeks, and the order quan- tity is 50. What action should be taken? Week 1 2 3 4 20 15 15 20 40 Gross Requirements Projected Available Net Requirements Planned Order Receipt Planned Order Release