Question: 44. The project has had some risks occur which required it to draw from its contingency reserve. The project manager is analyzing how much reserve

44. The project has had some risks occur which required it to draw from its contingency reserve. The project manager is analyzing how much reserve is left to make sure that it's adequate for the risks that remain. What risk management process is being performed? Identify Risks Plan Risk Management Perform Quantitative Risk Analysis . Monitor Risk