Question: 4Multiple Choice 1 point2. Jack's organization has many projects ongoing concurrently. He finds himself starting and stopping work on one task to go and work

4Multiple Choice 1 point2. Jack's organization has many projects ongoing concurrently. He finds himself starting and stopping work on one task to go and work on another task, and then return to the work on the original task. Jack is experiencingC. multitaskingD. excessive work burdenA.flexible taskingB. poor schedulingE. burnoutClear my selection