Question: ( 5 0 points ) - Project Management Schedule the following activities using CPM: table [ [ Activity , Immediate Predecessor,Time ( Weeks )

(50 points)-Project Management
Schedule the following activities using CPM:
\table[[Activity,Immediate Predecessor,Time (Weeks)],[A,-,1],[B,A,4],[C,A,3],[D,B,2],[E,C, D,5],[F,D,2],[G,F,2],[H,E, G,3]]
a) Draw the network (5 points)
b) What is the critical path? (15 points)
c) How many weeks will it take to complete the project? (15 points)
d) Which activities have slack, and how much? (15 points)
2.(50 points)-Forecasting
What strategies do supermarkets, airlines, hospitals, banks, and cereal manufacturers use to influence demand?
Please provide 1 strategy for each and explain that strategy.
 (50 points)-Project Management Schedule the following activities using CPM: \table[[Activity,Immediate Predecessor,Time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!