Question: 5 0 % Station 1 Station 2 5 0 % Station 3 Station 4 . 7 . 8 1 . 0 . 9 The system

50%
Station 1 Station 250% Station 3
Station 4 .7
.8
1.0
.9 The system above consists of a sequence of 4 stations. The cycle times in minutes for processing one unit of work are shown for each station. After the second station, 50% of the units are discarded due to quality problems. Work enters the system at a rate of I unit per minute.
a. Which station is the bottleneck?
b. Why?
c. What is the throughput capacity of the system?
If the yield loss fraction is reduced from 50%, what is the impact on other stations